ARTICLE 10
1 . IN OPEN PROCEDURE , THE TIME LIMIT FOR THE RECEIPT OF TENDERS FIXED BY THE CONTRACTING AUTHORITIES SHALL BE NOT LESS THAN 36 DAYS FROM THE DATE OF DISPATCH OF THE NOTICE . 2 . PROVIDED THEY HAVE BEEN REQUESTED IN GOOD TIME , THE CONTRACT DOCUMENTS AND SUPPORTING DOCUMENTS MUST BE SENT TO THE SUPPLIERS BY THE CONTRACTING AUTHORITIES OR COMPETENT DEPARTMENTS WITHIN FOUR WORKING DAYS OF RECEIVING THEIR APPLICATION . 3 . PROVIDED IT HAS BEEN REQUESTED IN GOOD TIME , ADDITIONAL INFORMATION RELATING TO THE CONTRACT DOCUMENTS MUST BE SUPPLIED BY THE CONTRACTING AUTHORITIES NOT LATER THAN SIX DAYS BEFORE THE FINAL DATE FIXED FOR RECEIPT OF TENDERS . 4 . WHERE TENDERS CAN ONLY BE MADE AFTER A VISIT TO THE SITE OR AFTER ON-THE-SPOT INSPECTION OF THE DOCUMENTS SUPPORTING THE CONTRACT DOCUMENTS , THE TIME LIMIT LAID DOWN IN PARAGRAPH 1 SHALL BE EXTENDED ACCORDINGLY .
← art_9__para · All articles · art_10__para →
Source: EUR-Lex (Cellar) · retrieved 2026-11-10 · Text as adopted (Official Journal); later amendments are not incorporated in this text.