1.

The external wall and roof of tanks above ground must be painted in a colour with a total radiant heat reflectance of 70 % or more. These operations may be programmed so as to be carried out as part of the usual maintenance cycles of the tanks within a period of three years. Member States may grant a derogation from this provision where required for the protection of special landscape areas which have been designated by national authority. This provision shall not apply to tanks linked to a vapour recovery unit which conforms with the requirements set out in Annex II, point 2.

National law under this provision

2 national measures recorded under this provision, in 1 form — sign in to view the analysis.