4.

Transmission system operators and distribution system operators shall be required to provide any new producer wishing to be connected with a comprehensive and detailed estimate of the costs associated with the connection. Member States may allow producers of electricity from renewable energy sources wishing to be connected to the grid to issue a call for tender for the connection work.

National law under this provision

2 national measures recorded under this provision, in 1 form — sign in to view the analysis.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-31 · Text as adopted (Official Journal); later amendments are not incorporated in this text.