6.
Any party having a complaint against a transmission, LNG or distribution system operator with respect to the issues mentioned in paragraphs 1, 2 and 4 and in Article 19 may refer the complaint to the regulatory authority which, acting as dispute settlement authority, shall issue a decision within two months after receipt of the complaint. This period may be extended by two months where additional information is sought by the regulatory authorities. This period may be extended with the agreement of the complainant. Such a decision shall have binding effect unless and until overruled on appeal.