Allocations to operators shall be made upon demonstration that an investment selected in accordance with the rules of the competitive bidding process has been carried out. Where an investment leads to additional electricity generation capacity, the operator concerned shall also demonstrate that a corresponding amount of electricity-generation capacity with higher emission intensity has been decommissioned by it or another associated operator by the start of operation of the additional capacity.