In the case of hydroelectric power production project activities with a generating capacity exceeding 20 MW, Member States shall, when approving such project activities, ensure that relevant international criteria and guidelines, including those contained in the World Commission on Dams November 2000 Report ‘Dams and Development — A New Framework for Decision-Making’, will be respected during the development of such project activities.