Article 7

Procedures for granting and refusing requests for authorisation 1. The competent authority shall not grant authorisation unless and until such time as it is fully satisfied that the applicant complies with all requirements under the provisions adopted pursuant to this Directive. 2. The investment firm shall provide all information, including a programme of operations setting out inter alia the types of business envisaged and the organisational structure, necessary to enable the competent authority to satisfy itself that the investment firm has established, at the time of initial authorisation, all the necessary arrangements to meet its obligations under the provisions of this Chapter. 3. An applicant shall be informed, within six months of the submission of a complete application, whether or not authorisation has been granted.