2.
The total amount paid as pre-financing shall be reimbursed to the Commission by the body designated by the Member State if no application for payment under the operational programme is sent within 24 months from the date on which the Commission pays the first instalment of the pre-financing amount. The total contribution from the Funds to the operational programme shall not be affected by such reimbursement.
← art_82__para_1__point_e__text_1 · All articles · art_82__para_2__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-01 · Text as adopted (Official Journal); later amendments are not incorporated in this text.