6.
The permit shall contain measures relating to conditions other than normal operating conditions. Thus, where there is a risk that the environment may be affected, appropriate provision shall be made for start-up, leaks, malfunctions, momentary stoppages and definitive cessation of operations. The permit may also contain temporary derogations from the requirements of paragraph 4 if a rehabilitation plan approved by the competent authority ensures that these requirements will be met within six months and if the project leads to a reduction of pollution.