5.
All applications for an authorisation to place in service submitted in accordance with this Article shall be the subject of a decision by the national safety authority, to be taken as soon as possible and not later than: four months after submission of the technical file referred to in paragraph 2; where applicable, two months after provision of the additional information or risk analyses requested by the national safety authority pursuant to paragraph 4; where applicable, two months after provision of the results of the tests requested by the national safety authority pursuant to paragraph 4.