| 10 | A contract may provide for the construction of an additional asset at the option of the customer or may be amended to include the construction of an additional asset. The construction of the additional asset shall be treated as a separate construction contract when: (a) the asset differs significantly in design, technology or function from the asset or assets covered by the original contract; or (b) the price of the asset is negotiated without regard to the original contract price.