| 29 | An entity is generally able to make reliable estimates after it has agreed to a contract which establishes: (a) each party's enforceable rights regarding the asset to be constructed; (b) the consideration to be exchanged; and (c) the manner and terms of settlement. It is also usually necessary for the entity to have an effective internal financial budgeting and reporting system. The entity reviews and, when necessary, revises the estimates of contract revenue and contract costs as the contract progresses. The need for such revisions does not necessarily indicate that the outcome of the contract cannot be estimated reliably.