| 34 | Contract costs that are not probable of being recovered are recognised as an expense immediately. Examples of circumstances in which the recoverability of contract costs incurred may not be probable and in which contract costs may need to be recognised as an expense immediately include contracts: (a) that are not fully enforceable, i.e. their validity is seriously in question; (b) the completion of which is subject to the outcome of pending litigation or legislation; (c) relating to properties that are likely to be condemned or expropriated; (d) where the customer is unable to meet its obligations; or (e) where the contractor is unable to complete the contract or otherwise meet its obligations under the contract.