Member States shall require transmission system operators and distribution system operators to provide any new producer of energy from renewable sources wishing to be connected to the system with the comprehensive and necessary information required, including: a comprehensive and detailed estimate of the costs associated with the connection; a reasonable and precise timetable for receiving and processing the request for grid connection; a reasonable indicative timetable for any proposed grid connection. Member States may allow producers of electricity from renewable energy sources wishing to be connected to the grid to issue a call for tender for the connection work.