4.
Member States may provide that the contracting authority/entity may ask or be required to ask the successful tenderer to subcontract to third parties a share of the contract. The contracting authority/entity that imposes such subcontracting shall express this minimal percentage in the form of a range of values, comprising a minimum and maximum percentage. The maximum percentage may not exceed 30 % of the value of the contract. Such a range shall be proportionate to the object and value of the contract and the nature of the industry sector involved, including the level of competition in that market and the relevant technical capabilities of the industrial base. Any percentage of subcontracting falling within the range of values indicated by the contracting authority/entity shall be considered to fulfil the subcontracting requirement set out in this paragraph. Tenderers may propose to subcontract a share of the total value which is above the range required by the contracting authority/entity. The contracting authority/entity shall ask tenderers to specify in their tender which part or parts of their offer they intend to subcontract to fulfil the requirement referred to in the first subparagraph. The contracting authority/entity may ask or may be required by a Member State to ask tenderers also to specify which part or parts of their offer they intend to subcontract beyond the required percentage, as well as the subcontractors they have already identified. The successful tenderer shall award subcontracts corresponding to the percentage which the contracting authority/entity requires it to subcontract in accordance with the provisions of Title III.
← art_21__para_3__text_1 · All articles · art_21__para_4__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-11 · Text as adopted (Official Journal); later amendments are not incorporated in this text.