(d)
insofar as is strictly necessary when, for reasons of extreme urgency brought about by events unforeseeable by the contracting authorities/entities in question, the time-limit for the restricted procedure or the negotiated procedure with publication of a contract notice, including the shortened time-limits as referred to in Article 33(7), cannot be complied with. The circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority/entity;