art_34__para_4__text_1
The additional information on the contract documents, the descriptive document and/or the supporting documents shall be sent by the contracting authority/entity or the competent department not less than six days before the deadline fixed for the receipt of tenders, provided that it is requested in good time. In the event of a restricted or an accelerated procedure, that period shall be four days.