lexiara

3. Coordination

3.1. Capacity allocation at an interconnection shall be coordinated and implemented using common allocation procedures by the TSOs involved. In cases where commercial exchanges between two countries (TSOs) are expected to affect physical flow conditions in any third-country (TSO) significantly, congestion-management methods shall be coordinated between all the TSOs so affected through a common congestion-management procedure. National regulatory authorities and TSOs shall ensure that no congestion-management procedure with significant effects on physical electric power flows in other networks is devised unilaterally. 3.2. A common coordinated congestion-management method and procedure for the allocation of capacity to the market at least annually, monthly and day-ahead shall be applied by 1 January 2007 between countries in the following regions: Northern Europe (i.e. Denmark, Sweden, Finland, Germany and Poland), North-West Europe (i.e. Benelux, Germany and France), Italy (i.e. Italy, France, Germany, Austria, Slovenia and Greece), Central Eastern Europe (i.e. Germany, Poland, Czech Republic, Slovakia, Hungary, Austria and Slovenia), South-West Europe (i.e. Spain, Portugal and France), UK, Ireland and France, Baltic states (i.e. Estonia, Latvia and Lithuania). At an interconnection involving countries belonging to more than one region, the congestion-management method applied may differ in order to ensure the compatibility with the methods applied in the other regions to which those countries belong. In that case, the relevant TSOs shall propose the method which shall be subject to review by the relevant regulatory authorities. 3.3. The regions referred to in point 2.8. may allocate all interconnection capacity through day-ahead allocation. 3.4. Compatible congestion-management procedures shall be defined in all those seven regions with a view to forming a truly integrated internal market in electricity. Market participants shall not be confronted with incompatible regional systems. 3.5. With a view to promoting fair and efficient competition and cross-border trade, coordination between TSOs within the regions set out in point 3.2. shall include all the steps from capacity calculation and optimisation of allocation to secure operation of the network, with clear assignments of responsibility. Such coordination shall include, in particular: the use of a common transmission model dealing efficiently with interdependent physical loop-flows and having regard to discrepancies between physical and commercial flows, allocation and nomination of capacity to deal efficiently with interdependent physical loop-flows, identical obligations on capacity holders to provide information on their intended use of the capacity, i.e. nomination of capacity (for explicit auctions), identical timeframes and closing times, identical structure for the allocation of capacity among different timeframes (for example, 1 day, 3 hours, 1 week, etc.) and in terms of blocks of capacity sold (amount of power in MW, MWh, etc.), consistent contractual framework with market participants, verification of flows to comply with the network security requirements for operational planning and for real-time operation, accounting and settlement of congestion-management actions. 3.6. Coordination shall also include the exchange of information between TSOs. The nature, time and frequency of information exchange shall be compatible with the activities set out in point 3.5 and the functioning of the electricity markets. That information exchange shall, in particular, enable the TSOs to make the best possible forecast of the global network situation in order to assess the flows in their network and the available interconnection capacities. Any TSO collecting information on behalf of other TSOs shall give back to the participating TSO the results of the collection of data.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-29 · Text as adopted (Official Journal); later amendments are not incorporated in this text.