At an interconnection involving countries belonging to more than one region, the congestion-management method applied may differ in order to ensure the compatibility with the methods applied in the other regions to which those countries belong. In that case, the relevant TSOs shall propose the method which shall be subject to review by the relevant regulatory authorities.