rec_7
(7) In order to ensure optimal management of the electricity transmission network and to allow trading and supplying electricity across borders in the Community, a European Network of Transmission System Operators for Electricity (the ENTSO for Electricity), should be established. The tasks of the ENTSO for Electricity should be carried out in compliance with Community competition rules which remain applicable to the decisions of the ENTSO for Electricity. The tasks of the ENTSO for Electricity should be well-defined and its working method should ensure efficiency, transparency and the representative nature of the ENTSO for Electricity. The network codes prepared by the ENTSO for Electricity are not intended to replace the necessary national network codes for non-cross-border issues. Given that more effective progress may be achieved through an approach at regional level, transmission system operators should set up regional structures within the overall cooperation structure, whilst ensuring that results at regional level are compatible with network codes and non-binding ten-year network development plans at Community level. Member States should promote cooperation and monitor the effectiveness of the network at regional level. Cooperation at regional level should be compatible with progress towards a competitive and efficient internal market in electricity.
← rec_6 · All articles · rec_8 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-29 · Text as adopted (Official Journal); later amendments are not incorporated in this text.