art_5__para_1__point_b__text_1
the measures, volumes, capacities and the timing needed to fulfil the infrastructure and supply standards, as laid down in Articles 6 and 8, including where applicable, the extent to which demand-side measures can sufficiently compensate, in a timely manner, for a supply disruption as referred to in Article 6(2), the identification of the single largest gas infrastructure of common interest in the case of application of Article 6(3) and any increased supply standard under Article 8(2);
← (b) · All articles · (c) →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.