1.

For each cross-border interconnection between Member States, except for those exempted under Article 6(5)(a) and except where bi-directional capacity already exists or is under construction and no enhancement has been requested by one or more Member States for security of supply reasons, transmission system operators shall, not later than 3 March 2012, submit to their Member States or, where Member States so provide, their Competent Authorities or their regulatory authorities (together referred to in this Article as the ‘authorities concerned’), after consulting with all other transmission system operators concerned: a proposal for bi-directional capacity concerning the reverse direction (reverse flow capacity); or a request for an exemption from the obligation to enable bi-directional capacity.