Article 4 › 6
Member States shall ensure that the competent authority makes its determination as soon as possible and within a period of time not exceeding 90 days from the date on which the developer has submitted all the information required pursuant to paragraph 4. In exceptional cases, for instance relating to the nature, complexity, location or size of the project, the competent authority may extend that deadline to make its determination; in that event, the competent authority shall inform the developer in writing of the reasons justifying the extension and of the date when its determination is expected.
1 national measure recorded under this provision, in 1 form — sign in to view the analysis.