5.
Where an operator of the service facility referred to in point 2 of Annex II encounters conflicts between different requests, it shall attempt to meet all requests in so far as possible. If no viable alternative is available, and it is not possible to accommodate all requests for capacity for the relevant facility on the basis of demonstrated needs, the applicant may complain to the regulatory body referred to in Article 55 which shall examine the case and take action, where appropriate, to ensure that an appropriate part of the capacity is granted to that applicant.