In the case of particularly complex contracts, where the contracting authority considers that direct use of the open procedure or the existing arrangements governing the restricted procedure will not allow the contract to be awarded to the tender offering best value for money, it may make use of the competitive dialogue referred to in Article 29 of Directive 2004/18/EC. A contract is considered to be ‘particularly complex’ where the contracting authority is not objectively able to define the technical means capable of satisfying the needs or objectives or able to specify the legal or financial make-up of the project.