If, for a given contract, tenders appear to be abnormally low, the contracting authority shall, before rejecting such tenders on that ground alone, request in writing details of the constituent elements of the tender which it considers relevant and shall verify those constituent elements, after due hearing of the parties, taking account of the explanations received. These details may relate in particular to compliance with the provisions relating to employment protection and working conditions in force at the place where the work, service or supply is to be performed.