2.

Provided that the request was made in good time before the deadline for submission of tenders, additional information relating to the specification or the descriptive documents or additional documents shall be supplied simultaneously to all economic operators who have requested the specification or expressed interest in taking part in a dialogue or submitting a tender as soon as possible and no later than six calendar days before the deadline for the receipt of tenders or, in the case of requests for information received less than eight calendar days before the deadline for receipt of tenders, as soon as possible after receipt of the request. Contracting authorities are not bound to reply to requests for additional information made less than five working days before the deadline for submission of tenders.