1.
Where duly substantiated urgency renders impracticable the minimum time limits laid down in Article 152(3) for restricted procedures and negotiated procedures where a contract notice is published, contracting authorities may set the following time limits, expressed in calendar days: a time limit for the receipt of requests to participate which may not be less than 15 days from the date on which the contract notice is dispatched or 10 days if the notice is sent to the Publications Office electronically; a time limit for the receipt of tenders which may not be less than 10 days from the date of dispatch of the invitation to tender.
← Article 154 · All articles · art_154__para_1__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.