1.

For the purposes of calculating the estimated amount of a contract, the contracting authority shall include the contractors total estimated remuneration. Where a contract provides for options or possible renewal, the basis for calculation shall be the maximum amount authorised, including the use of option clauses and renewal. This estimate shall be made when the contract notice is sent or, where there is no such publicity, when the contracting authority initiates the award procedure.