3.
A performance guarantee may be required by the contracting authority for an amount set in the tender file and corresponding to between 5 and 10 % of the total value of the contract for supply and works contracts. This guarantee shall be determined on the basis of objective criteria such as the type and value of the contract. However, a performance guarantee shall be required where the following thresholds are exceeded: EUR 345000 for works contracts, EUR 150000 for supply contracts. The guarantee shall remain valid at least until final acceptance of the supplies and works. If the contract is not properly performed the entire guarantee shall be retained.