3.
In international restricted procedures, the time limit for receipt of requests to participate shall be no less than 30 days from the date on which the contract notice is published. The period between the date on which the letter of invitation is sent and the final date for the receipt of tenders shall be no less than 50 days. However, in certain exceptional cases other time limits may be authorised.
← art_275__para_2__text_1 · All articles · art_275__para_3__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.