art_14__para_2
2. In the event that a mobile non-production installation is to be used for carrying out well operations, the internal emergency response plan for the installation shall take into account the risk assessment undertaken during the preparation of the notification of well operations to be submitted pursuant to point (h) of Article 11(1). Where the internal emergency response plan has to be amended due to the particular nature or location of the well, Member States shall ensure that the operator of the well submits the amended internal emergency response plan, or an adequate description thereof, to the competent authority to complement the relevant notification of well operations.
1 national measure recorded under this provision, in 1 form — sign in to view the analysis.
← art_14__para_1 · All articles · art_14__para_3 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-12 · Text as adopted (Official Journal); later amendments are not incorporated in this text.