art_142__para_1__text_1
CRD IV
Where an institution fails to meet its combined buffer requirement, it shall prepare a capital conservation plan and submit it to the competent authority no later than five working days after it identified that it was failing to meet that requirement, unless the competent authority authorises a longer delay up to 10 days.
← (1) · All articles · art_142__para_1__text_2 →
Source: EUR-Lex (Cellar) · retrieved 2026-09-25 · Text as adopted (Official Journal); later amendments are not incorporated in this text.