art_12__para_4__text_1
Within six months of the date on which the last investment request was received by the national regulatory authorities concerned, the national regulatory authorities shall, after consulting the project promoters concerned, take coordinated decisions on the allocation of investment costs to be borne by each system operator for the project, as well as their inclusion in tariffs. The national regulatory authorities may decide to allocate only part of the costs, or may decide to allocate costs among a package of several projects of common interest.
← 4. · All articles · art_12__para_4__text_2 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.