1.
Project promoters shall draw up an implementation plan for projects of common interest, including a timetable for each of the following: feasibility and design studies; approval by the national regulatory authority or by any other authority concerned; construction and commissioning; the permit granting schedule referred to in Article 10(4)(b).
← Article 5 · All articles · art_5__para_1__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.