4.

TSOs or, if applicable, transmission capacity allocators, shall provide a yearly report to the ENTSO for Electricity indicating: the main critical network elements limiting the offered capacity; the control area(s) which the critical network elements belong to; the extent to which relieving the critical network elements would increase the offered capacity; all possible measures that could be implemented to increase the offered capacity, together with their estimated costs. When preparing the report TSOs may choose not to identify the asset concerned and specify its location if it is classified as sensitive critical infrastructure protection related information in their Member States as provided for in point (d) of Article 2 of Directive 2008/114/EC. TSOs or, if applicable, transmission capacity allocators shall be considered as primary owners of the report they provide.