lexiara

1.

For their control areas, TSOs shall calculate and provide the following information to the ENTSO for Electricity: actual generation output (MW) per market time unit and per generation unit of 100 MW or more installed generation capacity; aggregated generation output per market time unit and per production type; actual or estimated wind and solar power generation (MW) in each bidding zone per market time unit; aggregated weekly average filling rate of all water reservoir and hydro storage plants (MWh) per bidding zone including the figure for the same week of the previous year.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.