(b)
changes in actual availability of a consumption unit with a power rating of 100 MW or more, specifying: bidding zone, available capacity per market time unit during the event, reason for the unavailability, the start date and the estimated end date (day, hour) of the change in availability.
← art_7__para_1__point_a__text_2 · All articles · art_7__para_1__point_b__text_1 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.