The approval by the Commission under the second subparagraph of paragraph 1 and paragraph 2 shall be conditional on the first works contract being concluded, or, in the case of operations implemented under PPP structures, on the signing of the PPP agreement between the public body and the private sector body, within three years of the date of the approval. At the duly motivated request of the Member State, in particular in the case of delays resulting from administrative and legal proceedings related to the implementation of major projects, and made within the three year period, the Commission may adopt a decision, by means of an implementing act, on the extension of the period by not more than two years.