lexiara

art_22__para_6__text_1

Where there is evidence, resulting from the performance review for a priority, that there has been a serious failure in achieving that priority's milestones relating only to the financial and output indicators and key implementation steps set out in the performance framework and that that failure is due to clearly identified implementation weaknesses, which the Commission had previously communicated pursuant to Article 50(8) following close consultations with the Member State concerned, and that Member State has failed to take the necessary corrective action to address such weaknesses, the Commission may, not earlier than five months after such communication, suspend all or part of an interim payment of a priority of a programme in accordance with the procedure laid down in the Fund-specific rules.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-10-29 · Text as adopted (Official Journal); later amendments are not incorporated in this text.