3.
The negotiated procedure without prior publication may be used for public supply contracts: where the products involved are manufactured purely for the purpose of research, experimentation, study or development; however, contracts awarded pursuant to this point shall not include quantity production to establish commercial viability or to recover research and development costs; for additional deliveries by the original supplier which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance; the duration of such contracts as well as that of recurrent contracts shall not, as a general rule, exceed three years; for supplies quoted and purchased on a commodity market; for the purchase of supplies or services on particularly advantageous terms, from either a supplier which is definitively winding up its business activities, or the liquidator in an insolvency procedure, an arrangement with creditors, or a similar procedure under national laws or regulations.
← (c) · All articles · (a) →
Source: EUR-Lex CELLAR · retrieved 2026-09-04 · Text as consolidated on 2026-01-01; changes after this date are not shown.