(d)

where a new contractor replaces the one to which the contracting authority had initially awarded the contract as a consequence of either: an unequivocal review clause or option in conformity with point (a); universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or in the event that the contracting authority itself assumes the main contractor’s obligations towards its subcontractors where this possibility is provided for under national legislation pursuant to Article 71;