Provided that it has been requested in good time, the contracting entities shall supply to all tenderers taking part in the procurement procedure additional information relating to the specifications and any supporting documents not later than six days before the time limit fixed for the receipt of tenders. In the event of an accelerated open procedure as referred to in Article 45(3), that period shall be four days.