Article 89 › 1 › b
for additional works, services or supplies by the original contractor, irrespective of their value, that have become necessary and were not included in the initial procurement where a change of contractor: (i) cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, software, services or installations procured under the initial procurement; and (ii) would cause significant inconvenience or substantial duplication of costs for the contracting entity;