BRRD

If the institution fails to submit a revised recovery plan, or if the competent authority determines that the revised recovery plan does not adequately remedy the deficiencies or potential impediments identified in its original assessment, and it is not possible to adequately remedy the deficiencies or impediments through a direction to make specific changes to the plan, the competent authority shall require the institution to identify within a reasonable timeframe changes it can make to its business in order to address the deficiencies in or impediments to the implementation of the recovery plan.