When adopting a resolution scheme, the Board, the Council and the Commission shall take into account and follow the resolution plan as referred to in Article 8 unless the Board assesses, taking into account the circumstances of the case, that the resolution objectives will be achieved more effectively by taking actions which are not provided for in the resolution plan.