art_20__para_5__text_1
At the time when two or more adjacent capacity calculation regions in the same synchronous area implement a capacity calculation methodology using the flow-based approach for the day-ahead or the intraday market time-frame, they shall be considered as one region for this purpose and the TSOs from this region shall submit within six months a proposal for applying a common capacity calculation methodology using the flow-based approach for the day-ahead or intraday market time-frame. The proposal shall provide for an implementation date of the common cross regional capacity calculation methodology of no longer than 12 months after the implementation of the flow-based approach in these regions for the methodology for the day-ahead market time-frame, and 18 months for the methodology for the intraday time-frame. The timelines indicated in this paragraph may be adapted in accordance with paragraph 6.
← 5. · All articles · art_20__para_5__text_2 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-01 · Text as adopted (Official Journal); later amendments are not incorporated in this text.