TSOs may jointly request the competent regulatory authorities to apply the coordinated net transmission capacity approach in regions and bidding zone borders other than those referred to in paragraphs 2 to 4, if the TSOs concerned are able to demonstrate that the application of the capacity calculation methodology using the flow-based approach would not yet be more efficient compared to the coordinated net transmission capacity approach and assuming the same level of operational security in the concerned region.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-01 · Text as adopted (Official Journal); later amendments are not incorporated in this text.