3.

If a review is launched in accordance with paragraph 1(d), the following conditions shall apply: the geographic area in which bidding zone configuration is assessed shall be limited to the control area of the relevant TSO, including interconnectors; the TSO of the relevant control area shall be the only TSO participating in the review; the competent regulatory authority shall be the only regulatory authority participating in the review; the relevant TSO and regulatory authority, respectively, shall give the neighbouring TSOs and regulatory authorities mutually agreed prior notice of the launch of the review, giving reasons; and the conditions for the review shall be specified, and the results of the review and proposal for the relevant regulatory authorities shall be published.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-01 · Text as adopted (Official Journal); later amendments are not incorporated in this text.