3.

Each TSO may redispatch all available generation units and loads in accordance with the appropriate mechanisms and agreements applicable to its control area, including interconnectors. By 26 months after the regulatory approval of capacity calculation regions, all TSOs in each capacity calculation region shall develop a report, subject to consultation in accordance with Article 12, assessing the progressive coordination and harmonisation of those mechanisms and agreements and including proposals. The report shall be submitted to their respective regulatory authorities for their assessment. The proposals in the report shall prevent these mechanisms and agreements from distorting the market.

· All articles ·

Source: EUR-Lex (Cellar) · retrieved 2026-11-01 · Text as adopted (Official Journal); later amendments are not incorporated in this text.